REHABTech conducts clinical, technical, engineering and information technology services with a number of collaborative centres.
It does this with the financial assistance of
REHABTech Supporters.
REHABTech Quick find

Site updated : 26th August, 2008
NIC- Administration Cost  
 Proposed National indicator of Prosthesis Cost

Cost of administration for NIC

At the Feedback Forum of representatives from the prosthetic industry  on Wednesday, 3 November 1999  at 3.05pm, one of the points that was discussed and generally agreed to was that the NIC from www.alsa.org.au should reflect the cost of administration.

A suggestion was to add the cost of administration of the respective ALSs to the average cost of each type of prosthesis as a percentage of the administrative costs versus the total cost funding the artificial limb services.

It was agreed that there are variations in what that administration provides, however an averaged indicative figure for the 1st of January 2000 may be a useful starting point.

Proposal

Each State and /or territory indicated the administrative percentage as at 1st of January 2000. (Other associated costs have also been added.)

This percentage has been added to the National Indicator of cost on the website and gives a "better" indication of cost of a particular limb.

(Please remember this is only a guide and may serve to help each administrator gauge what their respective administrative cost is as compared to the total budget paid out on prostheses.)

As with other aspects of the website, it will not be possible to identify what the administrative cost of any particular scheme is without contacting that State or Territory direct.

Example of how it has been derived -  These figures are just made up !!!

As at 1st of January 2000

State/Terr.
Total Budget
$ 000
Administrative cost estimate.
$ 000
%
A
5,500
450

B
520
90

C
2,000
120

D
1,500
110

E
2,800
260

Etc….
Etc….
Etc….
Etc….
Other Costs
-
-
-
XX
-
50
-
YY
 
120
-
Etc….
Etc….
Etc….
Etc….
Total
17,300
1,794
10.37

The figure that appears on the website is 10.37% and it appears as one of the structure line items on the National Indicator of Cost.



Return to ALS Managers' Forum Home page. 


 
Copyright © 2003 Monash University ABN 12 377 614 012 - Caution - Privacy - CRICOS Provider Number: 00008C
Last updated: 2009 - Maintained by webmaster-rehabtech@eng.monash.edu.au - Accessibility information

REHABTech - Centre for Biomedical Engineering
Dept. of Electrical And Computer Systems Engineering
Monash University

Building 35 Room G19
Clayton Vic AUSTRALIA 3800
Tel: 61 3 9905 3466
Fax: 61 3 9905 4069
E-mail: rehab.tech@eng.monash.edu.au
Internet: http://www.monash.edu.au/rehabtech